Exam PMP topic 1 question 1180 discussion

Actual exam question from PMI's PMP
Question #: 1180
Topic #: 1
[All PMP Questions]

During the initiation stage of a multimedia exhibition-design project, the project manager is developing the project management plan. What should the project manager do to complete this task?

  • A. Initiate a survey to solicit end-customer opinions and prioritize exhibition contents.
  • B. Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract.
  • C. Benchmark other similar exhibitions' deliverable lists and final outcomes.
  • D. Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 4 days ago
Selected Answer: D
D. Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: D
This is D
upvoted 2 times
...
ccfdeaa
3 months, 1 week ago
Selected Answer: C
Benchmark help to know more about the other product on market, so can help to define requirements
upvoted 1 times
...
Aditech
7 months, 1 week ago
D During the initiation stage of a multimedia exhibition-design project, the project manager should develop the project management plan by identifying stakeholders, defining objectives, creating a scope statement and project charter, identifying risks, and integrating all planning documents into a comprehensive plan.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...