During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?

  • A. Agree with the project team that the new requirements will be applied to the next project, not the one already under development.
  • B. Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.
  • C. Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reaction time.
  • D. Stop the project until someone in the organization can identify all the new requirements and how they impact the project.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 4 days ago
Selected Answer: B
B. Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions
upvoted 1 times
...
Aditech
7 months, 1 week ago
B According to the PMBOK, when new legal requirements emerge during project development in a dynamic market environment, and compliance with project deliverables is uncertain, the project manager should assess the impact, consult experts, update the project plan, communicate with stakeholders, mitigate risks, and continuously monitor and adapt to ensure compliance throughout the project lifecycle. Adigun.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...