A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other. What should the project manager do?

  • A. Review the organizational culture, structure, and governance.
  • B. Coordinate a meeting with regional managers to ask for support.
  • C. Review lessons learned from previous projects that used the same team.
  • D. Coordinate a meeting to understand the situation and resolve any conflicts.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 4 days ago
Selected Answer: D
D. Coordinate a meeting to understand the situation and resolve any conflicts
upvoted 1 times
...
Aditech
7 months, 1 week ago
D In accordance with the PMBOK, when team members from different regions are reluctant to collaborate during the planning phase of a global project, the project manager should facilitate communication, promote team building, establish common goals, mediate disputes, provide cultural sensitivity training, create clear communication channels, and seek executive support if needed.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.