Exam PMP topic 1 question 1177 discussion

Actual exam question from PMI's PMP
Question #: 1177
Topic #: 1
[All PMP Questions]

At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

  • A. Defer all actions until the next workshop to keep the team focused on other higher priorities.
  • B. Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.
  • C. Review the critical path and update the project schedule with the newly identified tasks.
  • D. Follow up on each item as soon as possible to ensure timely completion and report the status to management.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 4 days ago
Selected Answer: B
B. Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress
upvoted 1 times
...
Aditech
7 months, 1 week ago
B According to the PMBOK, after a workshop to review project deliverables and generate follow-up action items, the project manager should document, prioritize, assign responsibilities, communicate, track progress, and review and close out completed actions. Adigun.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.