During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager react to ensure the project remains successful?

  • A. Thank the team member for raising this issue, log it, and move on to the next topic.
  • B. Punish the team member for providing negative data that will affect the team's morale.
  • C. Focus the discussion on recovery and ways to get back on track.
  • D. Act in a way to highlight the criticality of the situation.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 4 days ago
Selected Answer: C
C. Focus the discussion on recovery and ways to get back on track
upvoted 1 times
...
Aditech
7 months, 1 week ago
C In response to significant bad news about the project schedule during progress review meetings, the PMBOK advises the project manager to stay calm, listen, assess the impact, collaborate on solutions, adjust the plan if needed, communicate effectively, and monitor progress for success.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...