D
Assess the impact of the requested changes on project constraints, follow the change management process to evaluate and implement changes if feasible, or communicate constraints and discuss alternatives with the customer, according to PMBOK.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 week, 5 days agoKim222
3 months, 1 week agod370e49
2 months, 1 week agosidje
6 months agoAditech
7 months, 1 week ago