Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1194 discussion

Actual exam question from PMI's PMP
Question #: 1194
Topic #: 1
[All PMP Questions]

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

  • A. Reject the changes as the lead time is too short.
  • B. Check if the changes are covered in the statement of work (SOW).
  • C. Determine whether the project team is capable of making the changes.
  • D. Review the additional changes and perform integrated change control.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
1 month, 1 week ago
Selected Answer: D
Reality is A.
upvoted 1 times
d370e49
1 week, 1 day ago
Unfortunately this isn't reality, it's silly PMI world!
upvoted 1 times
...
...
sidje
4 months ago
Selected Answer: D
Selon le PMBOK, à chaque fois qu'un changement se présente le chef de projet doit en premier l'analyser et mesurer son impact.
upvoted 2 times
...
Aditech
5 months, 1 week ago
D Assess the impact of the requested changes on project constraints, follow the change management process to evaluate and implement changes if feasible, or communicate constraints and discuss alternatives with the customer, according to PMBOK.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...