A new relevant project stakeholder suggested a change to some of the project parameters midway through execution. What should the project manager do next?
A.
Reject the change because it is contrary to what was agreed to during earlier phases of the project.
B.
Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps.
C.
Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor.
D.
Accept the change and use contingency funds to implement this change with minimal schedule impacts.
D
According to the PMBOK Guide, the project manager should follow the established change management process to evaluate the proposed change's impact on the project's scope, schedule, budget, quality, and other parameters.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 week, 6 days agoKim222
2 months, 2 weeks agokevzzz
5 months, 2 weeks agoAditech
7 months, 1 week agoAditech
7 months, 1 week ago