Exam PMP topic 1 question 1167 discussion

Actual exam question from PMI's PMP
Question #: 1167
Topic #: 1
[All PMP Questions]

In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?

  • A. Raise this issue, and review and update the progress report for the next monthly project meeting.
  • B. Communicate with an officer in the environmental protection department to check if it is necessary.
  • C. Organize a meeting with the team and update the work breakdown structure (WBS).
  • D. Start the organization’s change control process via a change request.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 5 days ago
Selected Answer: D
D. Start the organization’s change control process via a change request
upvoted 1 times
...
Aditech
7 months, 2 weeks ago
Assess impact, communicate with stakeholders, evaluate scope feasibility, and coordinate with authorities to expedite permit process.
upvoted 1 times
...
Aditech
7 months, 2 weeks ago
B Communicate with an officer in the environmental protection department to check if it is necessary.
upvoted 3 times
ompk
6 months, 1 week ago
PM has already been communicated by the marine co. that the environmental work is must otherwise they would not give the work permit.So it is already communicated and this work is not a part of the project scope so it means the scope needs to be changed which means the required environmental work needs to be added in the scope so CHANGE REQUEST IS MUST which is why option D is the right choice to address the issue
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...