After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.
What should the project manager do?
victory108
2 weeks, 5 days agoAmirov
3 weeks, 2 days agoKim222
2 months, 3 weeks agoezzaariyouness
3 months agoLNX_RM_Admin
6 months agoAditech
7 months, 2 weeks agoAditech
7 months, 2 weeks ago