Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1209 discussion

Actual exam question from PMI's PMP
Question #: 1209
Topic #: 1
[All PMP Questions]

A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.

What should the project manager do next?

  • A. Review the terms and conditions of the contract.
  • B. Submit a change request to include the manual.
  • C. Review the stakeholder engagement plan.
  • D. Add the needed manual and update the risk log.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
mrwriting
Highly Voted 7 months, 2 weeks ago
Selected Answer: A
Review contract first
upvoted 5 times
...
victory108
Most Recent 1 month, 4 weeks ago
Selected Answer: A
A. Review the terms and conditions of the contract
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: A
A is alright
upvoted 1 times
...
ccfdeaa
3 months, 1 week ago
Selected Answer: A
Review 1st
upvoted 1 times
...
c8ee0e6
4 months, 2 weeks ago
Selected Answer: A
A is the correct answer.
upvoted 1 times
...
kevzzz
5 months, 3 weeks ago
Selected Answer: A
What should the project manager do next? The key word to this question is NEXT
upvoted 1 times
...
Tommy133
7 months, 1 week ago
Selected Answer: A
After reviewing the terms and conditions of the contract, the project manager can determine the next course of action based on the contract's content: If the contract explicitly includes the maintenance manual, there would be no need to submit a change request. Instead, the project manager should arrange for the creation and delivery of the maintenance manual, learn from the mistake, and take steps to prevent similar errors in the future. If the contract does not explicitly include the maintenance manual but the customer strongly insists on its inclusion, the project manager needs to communicate with the customer and may need to submit a change request. Additionally, updating the risk log to document this incident would be necessary.
upvoted 2 times
Kim222
2 months, 4 weeks ago
Good thx
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...