Question #: 1147
Topic #: 1
[All PMP Questions]

A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?

  • A. Consult with the project team members to gain their opinions.
  • B. Ask the project team to delay the kick-off while resolving the concern.
  • C. Meet with the project sponsor to obtain more information.
  • D. Request a copy of the project assumptions log for more insight.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 1 day ago
Selected Answer: C
C. Meet with the project sponsor to obtain more information
upvoted 1 times
...
sidje
6 months ago
Selected Answer: C
Le parrain du projet est généralement bien placé pour expliquer comment les objectifs et les avantages du projet s’intègrent dans la stratégie globale de l’organisation. Cette rencontre permet également de s'assurer que toutes les parties prenantes sont sur la même longueur d’onde et que le projet contribue de manière significative à la réalisation des buts stratégiques de l'organisation.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...