Question #: 1140
Topic #: 1
[All PMP Questions]

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?

  • A. Schedule a meeting with the project team member's functional manager and request the functional manager's support.
  • B. Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.
  • C. Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.
  • D. Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 3 days ago
Selected Answer: B
B. Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus
upvoted 1 times
...
Aditech
7 months, 2 weeks ago
B The project manager should listen to the team member's concerns, communicate with the project sponsor to clarify reasons behind the change, and facilitate open communication to find a mutually acceptable solution.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...