exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 889 discussion

Actual exam question from PMI's PMP
Question #: 889
Topic #: 1
[All PMP Questions]

An organization is transitioning to an agile project delivery approach. Each project is structured as a Scrum team. A project is in the initiation phase. In one of the workshops, a business subject matter expert (SME) indicated that the project may have legal constraints. The legal team was not identified as a stakeholder in the project brief.

What should the project lead do?

  • A. Ask the solutions architect to contact the legal department and create the epic(s) in the product backlog.
  • B. Advise the SME that there are no legal requirements identified in the project brief and continue the workshop.
  • C. Ask the project sponsor to contact the legal department and identify the legal impact.
  • D. Add the legal department to the list of stakeholders and contact them to discuss the project scope.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Selected Answer: D
The legal team was not identified as a stakeholder initially, but the SME's input highlights that there may be legal constraints. It is crucial to identify all relevant stakeholders early to ensure that their requirements and constraints are considered in the project. Furthermore, by contacting the legal department, the project team can clarify any legal considerations that need to be incorporated into the project scope. This will help in creating a more accurate and comprehensive project plan.
upvoted 2 times
...
maestro169
1 month, 2 weeks ago
Selected Answer: D
SME has identified legal constraints already. The legal department should be included in the stakeholder register and part of the stakeholders consulted.
upvoted 1 times
...
cookie98
2 months, 2 weeks ago
Selected Answer: C
Since the project sponser has direct engagement with the stakeholders, it would be smart to have them FIRST determine if they are impacted before adding them as a stakeholder. confirm before acting.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago