An organization is transitioning to an agile project delivery approach. Each project is structured as a Scrum team. A project is in the initiation phase. In one of the workshops, a business subject matter expert (SME) indicated that the project may have legal constraints. The legal team was not identified as a stakeholder in the project brief.
What should the project lead do?
UppersquareCapital
1 month agomaestro169
1 month, 2 weeks agocookie98
2 months, 2 weeks ago