Exam PMP topic 1 question 1104 discussion

Actual exam question from PMI's PMP
Question #: 1104
Topic #: 1
[All PMP Questions]

A project manager has been assigned to a global project involving regulatory bodies, government agencies, internal company leaders, the project team, and end users.

What should the project manager do to engage them all effectively?

  • A. Gather business requirements.
  • B. Check lessons learned from past projects.
  • C. Remove any bias that exists on the team.
  • D. Analyze the stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 6 days ago
Selected Answer: D
D. Analyze the stakeholders
upvoted 1 times
...
AzureFreak
8 months ago
Selected Answer: D
Will go with D. Analyze the stakeholders.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...