Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 997 discussion

Actual exam question from PMI's PMP
Question #: 997
Topic #: 1
[All PMP Questions]

A project sponsor has requested a trend analysis of all risks that the project has monitored over the past 12 months. What should the agile project manager do?

  • A. Extract this from the project risk register tracking tool and issues log
  • B. Refer the sponsor to the contract document
  • C. Organize a stakeholder meeting to brainstorm on general project risks
  • D. Share the annual report with the sponsor
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month, 1 week ago
Selected Answer: A
A. Extract this from the project risk register tracking tool and issues log This option directly addresses the sponsor's request by providing a trend analysis based on real data that has been tracked over the past 12 months. The project risk register and issues log are the appropriate sources for such information, as they contain a detailed history of risks and their management throughout the project.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: A
A. Extract this from the project risk register tracking tool and issues log
upvoted 1 times
...
Ngho
1 month, 2 weeks ago
A. Extract this from the project risk register tracking tool and issues log. The risk register and issues log are where risks are typically tracked, including how they've evolved over time. By extracting this data, the project manager can perform a trend analysis, showing how risks have been managed and any recurring patterns. This provides the sponsor with the requested analysis based on actual tracked data over the past 12 months. Sharing an annual report or referring to the contract document would not provide the detailed risk analysis the sponsor is looking for, and a brainstorming session isn't relevant to analyzing past trends.
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: A
A. Extract this from the project risk register tracking tool and issues log Pretty simple.
upvoted 1 times
...
dimo475
8 months, 1 week ago
Project managers conduct trend analysis of risk metrics, such as frequency and severity of identified risks, to track the effectiveness of risk management activities. By analyzing risk trends, they can anticipate potential risks, monitor the evolution of existing risks, and implement risk response strategies accordingly.
upvoted 1 times
...
dimo475
8 months, 1 week ago
Selected Answer: A
Option A, extracting the trend analysis from the project risk register tracking tool and issues log, is the most appropriate action for the Agile project manager to take in this scenario. In Agile project management, maintaining a risk register and issues log is common practice to track and manage project risks throughout the project lifecycle.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...