Exam PgMP topic 1 question 313 discussion

Actual exam question from PMI's PgMP
Question #: 313
Topic #: 1
[All PgMP Questions]

An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.
What should the program manager do next?

  • A. Assign resources to the schedule and report the revised delivery date to the project managers.
  • B. Work with the project managers to refine the project schedules and deliverables to align with the program milestones.
  • C. Revise the project schedules to meet the program schedule and communicate to stakeholders.
  • D. Integrate the project schedules into the program schedule and report the revised delivery date to the project managers.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
psvexam
1 month, 3 weeks ago
B is more appropriate
upvoted 1 times
...
tungdt
2 months, 2 weeks ago
B is the best answer
upvoted 1 times
tungdt
2 months, 2 weeks ago
After the project managers submit their preliminary schedules, the program manager should collaborate with them to refine these schedules and ensure that the deliverables align with the overall program milestones. This step is crucial for maintaining coherence and consistency across all projects within the program, ensuring that they contribute effectively to the accelerated timeline for bringing the product to market. This approach also helps identify and address any discrepancies or potential conflicts early in the process, facilitating smoother program execution.
upvoted 1 times
...
...
hanyulin
6 months, 1 week ago
Selected Answer: D
D is the right answer.
upvoted 1 times
...
hanyulin
6 months, 1 week ago
Selected Answer: D
D is a better answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...