Exam PMP topic 1 question 1102 discussion

Actual exam question from PMI's PMP
Question #: 1102
Topic #: 1
[All PMP Questions]

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

  • A. Stakeholders who disagree with the project so as to proactively manage their expectations.
  • B. Stakeholders who have been identified and who have needs and a potential impact on the project.
  • C. Stakeholders who are supporting the project in order to obtain additional resources.
  • D. Stakeholders who are selected by the project sponsor who have a potential impact on the project.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 6 days ago
Selected Answer: B
B. Stakeholders who have been identified and who have needs and a potential impact on the project
upvoted 1 times
...
AzureFreak
8 months ago
B. Stakeholders who have been identified and who have needs and a potential impact on the project.
upvoted 1 times
...
dimo475
8 months, 1 week ago
Selected Answer: B
B. Stakeholders who have been identified and who have needs and a potential impact on the project. In stakeholder engagement planning, it's crucial to include all stakeholders who have been identified and who have needs and a potential impact on the project. This includes stakeholders who support the project as well as those who oppose it.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...