Exam CAPM topic 1 question 418 discussion

Actual exam question from PMI's CAPM
Question #: 418
Topic #: 1
[All CAPM Questions]

A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team.

What should the project manager do next?

  • A. Escalate this issue to the project management office (PMO).
  • B. Reschedule the rollout to include the new requirements.
  • C. Escalate this issue to the project sponsor.
  • D. Reschedule the rollout to start with another business unit.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: C
In this scenario, the project manager should consider escalating this issue to the project sponsor. The project sponsor is typically responsible for providing direction and resources for the project, and they can make decisions regarding changes in project scope, such as the addition of new functionality requested by the business unit manager. By escalating the issue to the project sponsor, the project manager can seek guidance on how to proceed with the request while considering the project's objectives, timeline, and resources. It's important to address the business unit manager's request without compromising the project's progress. The project sponsor can help determine if the new functionality can be incorporated into the current project scope or if it should be considered for future iterations.
upvoted 1 times
...
ebbff63
4 months ago
Selected Answer: C
Ans: C The project sponsor has the authority to make decisions regarding scope changes and can provide guidance on how to proceed with the additional functionality request.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...