Calculate the schedule performance index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

  • A. 15
  • B. 0.5
  • C. 45
  • D. 2.0
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: D
SPI = Earned Value (EV) / Planned Value (PV) Given: EV = 30 PV = 15 Therefore, SPI = 30 / 15 = 2 So the answer is D: 2.0 Important note: An SPI greater than 1 indicates that the project is ahead of schedule.
upvoted 1 times
...
lamiaa
6 months, 2 weeks ago
this one of the questions in today's exam [ 03/12/2024
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...