Actual exam question from PMI's CAPM
Question #: 423
Topic #: 1
[All CAPM Questions]

During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?

  • A. Accept the customer's request and continue with elicitation of the new product features.
  • B. Decline any request by the customer and continue the project as initially planned.
  • C. Investigate the possibility of using the management reserve to pay for the extra hours the team will need to work.
  • D. Investigate the effect that such an integration will have on the project plan and propose a change request.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
lamiaa
7 months, 2 weeks ago
this one of the questions in today's exam [ 03/12/2024
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago