During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?
A.
Accept the customer's request and continue with elicitation of the new product features.
B.
Decline any request by the customer and continue the project as initially planned.
C.
Investigate the possibility of using the management reserve to pay for the extra hours the team will need to work.
D.
Investigate the effect that such an integration will have on the project plan and propose a change request.
this one of the questions in today's exam [ 03/12/2024
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
lamiaa
7 months, 2 weeks ago