Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 430 discussion

Actual exam question from PMI's CAPM
Question #: 430
Topic #: 1
[All CAPM Questions]

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

  • A. Retrospective
  • B. Daily standup
  • C. Backlog refinement review
  • D. Iteration planning
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
A. Retrospective A retrospective is a crucial meeting held at the end of each iteration in an adaptive project management environment to reflect on the completed iteration, identify what worked well, what didn't, and what can be improved for future iterations.
upvoted 1 times
...
lamiaa
6 months, 2 weeks ago
this one of the questions in today's exam [ 03/12/2024
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...