Question #: 433
Topic #: 1
[All CAPM Questions]

What should be completed when the work-in-progress (WIP) limit is reached and new work has been requested?

  • A. Decompose the work and add it to the backlog.
  • B. Put the request in a holding area.
  • C. Ask for the priority level of the new request.
  • D. Add the work to the backlog.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ebbff63
1 month ago
Selected Answer: B
B. Put the request in a holding area.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.