Question #: 39
Topic #: 1
[All PgMP Questions]

A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

  • A. Program risk
  • B. Program benefits
  • C. Program scope
  • D. Link to organizational strategy
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AmrKHALIL
1 month ago
Selected Answer: A
A. Program risk
upvoted 1 times
...
tungdt
5 months, 4 weeks ago
C is correct
upvoted 1 times
...
happykaur
9 months, 3 weeks ago
Selected Answer: C
From PGMP page 48 The business case may include details about the program outcomes, approved concept, issues, high-level risk and opportunity assessment, key assumptions, business and operational impact, cost benefit analysis, alternative solutions, financial analysis, intrinsic and extrinsic benefits, market demands or barriers, potential profits, social needs, environmental influences, legal implications, time to market, constraints, and the extent to which the program aligns with the organization’s strategic plan.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago