A project defined to be executed in four months is divided into eight iterations. During its first retrospective, the team realizes that only one member has experience doing a key project requirement.
What should the project manager do?
A.
Invite the team member to share experience in the next retrospective.
B.
Ask the sponsor to add team members with the required experience.
C.
Plan knowledge-sharing sessions within the team.
D.
Ask the sponsor for a training course for the team.
C. Plan knowledge-sharing sessions within the team.
Explanation: Organizing knowledge-sharing sessions allows the experienced team member to share their expertise with the rest of the team, enhancing overall capability and ensuring the project requirements can be met more effectively.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 week, 3 days ago517f9da
6 months, 1 week agoerkut57
9 months, 2 weeks ago