Why the other options are incorrect:
B. ❌ Common in Agile, compares items relative to one another (e.g., story points) — not algorithm-based or focused on cost.
C. ❌ Uses optimistic, pessimistic, and most likely estimates to calculate an average — it's about range-based estimation, not historical algorithmic models.
D. ❌ Also uses historical data but does not use algorithms — it’s expert judgment–based, using similar past projects for quick, high-level estimates.
Parametric estimating uses an algorithm or mathematical model to calculate costs or durations based on historical data and project parameters. For example, it might estimate costs based on the cost per unit of work multiplied by the number of units required.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
3Â weeks, 1Â day agoreve6669
6Â months agoAndrew_1980
1Â year agoflee
1Â year agoGoldenRetriever
1Â year agoebbff63
1Â year, 1Â month agoMouxx
1Â year, 3Â months agoMizbee
1Â year, 5Â months ago