Exam PMP topic 1 question 913 discussion

Actual exam question from PMI's PMP
Question #: 913
Topic #: 1
[All PMP Questions]

During a project kickoff meeting, the client indicates that the benefits of the project will become the most important revenue stream for the company. The client needs to find opportunities to deliver value to their company as soon as possible.

What should the project manager do?

  • A. Apply project schedule compression techniques to deliver benefits faster.
  • B. Plan project iterations taking into consideration value delivery.
  • C. Develop a project management plan to achieve the goals of the project faster.
  • D. Align the goals of the project with the revenue goals of the company.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 week, 2 days ago
Selected Answer: B
B. Plan project iterations taking into consideration value delivery
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: B
B. Plan project iterations taking into consideration value delivery. Explanation: Planning project iterations with a focus on value delivery ensures that the client receives incremental benefits as early as possible, aligning with their need to quickly generate revenue from the project.
upvoted 1 times
...
ChuksAz
9 months, 2 weeks ago
B. Plan project iterations taking into consideration value delivery. In an Agile project management context, planning project iterations with a focus on value delivery aligns with the Agile principles of delivering incremental value to the customer early and often. By planning iterations based on value, the project manager ensures that the most critical features and functionalities are prioritized and delivered in a way that provides tangible benefits to the client as soon as possible. While option A (applying project schedule compression techniques) and option C (developing a project management plan to achieve goals faster) may be valid considerations, option B is more specific to the Agile approach and emphasizes the importance of delivering value in a timely manner. Option D (aligning goals with revenue goals) is a broader concept that may be part of the overall strategy, but option B directly addresses the immediate need to focus on value delivery in project iterations.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...