Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 940 discussion

Actual exam question from PMI's PMP
Question #: 940
Topic #: 1
[All PMP Questions]

In a daily standup, the project lead notices that one of the senior developers is reassigning some of the easy backlog items to other team members, arguing that it is more efficient for the senior developers to work on complex items. What should the project lead do?

  • A. Include this practice in the next sprint review and discuss it with all of the team members.
  • B. Ask the senior developer to stop assigning tasks because that's the scrum master's job.
  • C. Support the senior developer's action and their authority over other team members.
  • D. Include this practice in the next sprint retrospective and discuss it with all of the team members.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 week, 1 day ago
Selected Answer: D
D. Include this practice in the next sprint retrospective and discuss it with all of the team members
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: D
D. Include this practice in the next sprint retrospective and discuss it with all of the team members. Explanation: Discussing this practice during the next sprint retrospective allows the entire team to provide input and evaluate whether this approach aligns with the team's goals and values. This promotes transparency, collaboration, and ensures that task assignments are handled in a way that benefits the entire team.
upvoted 1 times
...
Abdelmonm
10 months ago
Selected Answer: D
The sprint retrospective is a key opportunity for the team to reflect on their processes and identify improvements. If the project lead notices a change in task assignments during the daily standup, it's appropriate to bring it up during the retrospective. This allows the team to openly discuss the practice, share perspectives, and collaboratively decide whether it aligns with their agreed-upon processes and principles. The retrospective is a forum for continuous improvement, and discussing such issues can lead to adjustments in team practices for better efficiency and collaboration.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...