A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
A.
Work on the backlog activities with fewer story points.
B.
Ask for more resources to clear the backlog activities.
C.
Prioritize which backlog activities should be kept.
D.
Assign an owner for each backlog activity and track progress
Prioritizing backlog activities helps focus efforts and resources on delivering the highest value items first. This ensures that the most critical features or deliverables are addressed early in the project, maximizing the project's impact within the constraints of time and budget.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
4 weeks agoDavard
10 months ago