A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project.

To what level should the project manager decompose their project?

  • A. To the lowest level where cost and duration can be estimated and managed
  • B. To the level where the highest level of quality is maintained
  • C. To level four of the schedule for bridge construction
  • D. To the level where the bridge can be constructed safely
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
4 weeks ago
Selected Answer: A
A. To the lowest level where cost and duration can be estimated and managed
upvoted 1 times
...
dimo475
8 months, 1 week ago
ChatGPT sais: A. To the lowest level where cost and duration can be estimated and managed The purpose of creating a Work Breakdown Structure (WBS) is to decompose the project scope into smaller, more manageable components. These components are then used for estimating costs, defining schedules, assigning resources, and managing the project. The project manager should decompose the project to the lowest level where cost and duration can be estimated and managed effectively. This ensures that the project is broken down into a sufficient level of detail to accurately estimate the resources and time required for each component of the project. It also enables effective cost and schedule management throughout the project lifecycle.
upvoted 1 times
...
Davard
10 months ago
Selected Answer: A
It involves breaking down the project scope into manageable and measurable components, typically work packages or tasks, that can be assigned durations, resources, and costs.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...