Question #: 1065
Topic #: 1
[All PMP Questions]

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

  • A. Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.
  • B. Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product.
  • C. Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.
  • D. Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: B
B. Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product
upvoted 1 times
...
Davard
10 months ago
Selected Answer: B
B would allow the team to learn.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...