Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 899 discussion

Actual exam question from PMI's PMP
Question #: 899
Topic #: 1
[All PMP Questions]

Due to a change in market conditions, the business value for the original project requirements has changed. What should the project manager consider for execution?

  • A. Evaluate and work on small requirements to deliver business value.
  • B. Negotiate with the stakeholder to deliver with existing business value.
  • C. Continue as planned since changes will have no impact on the project.
  • D. Take into consideration the requirements with the modified business value.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 5 days ago
Selected Answer: D
Value = Evaluate the needs.
upvoted 1 times
...
Abdelmonm
8 months ago
Selected Answer: D
In response to a change in market conditions affecting business value, the project manager should consider adjusting the project execution plan to accommodate the modified business value. This may involve reevaluating priorities, focusing on the most valuable requirements, and adapting the project scope accordingly. Ignoring the impact of changed business value may lead to misalignment with stakeholder expectations and market needs.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...