An information technology (TT) team is responsible for the validation and release of a product developed by the agile development team. Due to other priorities for the IT learn, the releases are delayed.
What action should the project manager take?
A.
Work with the IT team to prioritize the validation and release of the new features.
B.
Deliver the features when the IT team is able to validate them.
C.
Escalate the issue from the IT team to management and get the validation prioritized.
D.
Request the IT team to immediately release the product and then validate the features.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month agoDavard
10 months ago