A few project team members are having issues understanding the requirements as described. Which action should be taken to resolve this issue?
A.
Review the requirements traceability matrix, the business analysis communications management plan, and set up a meeting with the business analyst and key stakeholders.
B.
Review the requirements traceability matrix and set up a meeting with the business analyst and key stakeholders.
C.
Review the project management plan and set up a meeting with the project manager and key stakeholders.
D.
Review the business analysis communications management plan and set up a meeting with the business analyst and key stakeholders.
To address the issue of understanding requirements, I recommend option A: Review the requirements traceability matrix, along with the business analysis communications management plan, and then set up a meeting with the business analyst and key stakeholders. The requirements traceability matrix (RTM) is a valuable tool in project management. It helps track all project requirements throughout product development, ensuring that each essential requirement is fulfilled and that no functionality is left unchecked during software testing. By reviewing the RTM and engaging with stakeholders, the team can gain clarity and alignment on project requirements.
correct answer is B. Review the requirements traceability matrix and set up a meeting with the business analyst and key stakeholders.
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
zvezdo
4 days, 9 hours agoVangelis_1980
8 months agoshubu2276
1 year, 2 months ago