Question #: 286
Topic #: 1
[All CAPM Questions]

An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.

Which of the following changes has caused this loss in productivity?

  • A. The team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.
  • B. Two of the team members have been working in silos using different methods to validate their performance.
  • C. Two of the team members were asked to do multitasking, which they did not do in the previous two sprints.
  • D. The team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: B
C. Two of the team members were asked to do multitasking, which they did not do in the previous two sprints. Explanation: Multitasking is generally detrimental to productivity. It leads to context switching, which can significantly reduce efficiency and output. The sudden introduction of multitasking to two team members would disrupt their workflow and negatively impact the overall team performance.
upvoted 1 times
...
shubu2276
8 months ago
Selected Answer: B
B. Two of the team members have been working in silos using different methods to validate their performance. In an adaptive or agile project management approach, team collaboration is crucial for successful project outcomes. Option B, where two team members are working in silos using different methods, indicates a lack of collaboration and coordination within the team. This can lead to reduced productivity, as it may result in duplicated efforts, miscommunication, and a lack of synergy. Options A, C, and D do not directly address issues related to team collaboration or coordination. Technical debt (option A) and multitasking (option C) are different concerns that can affect productivity, but they don't specifically address the collaboration aspect. The measurement of velocity (option D) using a tool introduced in the third sprint may affect metrics, but it doesn't directly point to collaboration issues within the team.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...