A project manager discovered that a component on the critical path is in danger of delay due to continuous disagreements between two developers. This personality-related issue can’t be resolved by the team.
What should the project manager do?
A.
Log the issue in the register and delay the development of the component.
B.
Log the issue in the register and ask the team to make a decision by voting.
C.
Log the issue in the register and escalate to the human resources (HR) manager.
D.
Log the issue in the register and let the developers resolve the conflict.
Asking the team to take a vote can have a knock-on effect on the behavior of the two developers against the team in which they are part of. Besides the question stated the “issue can’t be resolved by the team” so that’s ruled out B.
Delaying the development of the component is not a good option, so A is wrong.
D would have been a good answer, but since it’s a continuous disagreement between the two developers even with possible intervention with the Project Manager to resolve their conflict. Hence, the last course of action to answer this question is to escalate the issue with the HR Manager, so answer is C.
Me parece que B es una mejor opciĂłn , escalar a RH es muy drastico.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
4Â weeks agoKim222
2Â months, 3Â weeks agoLNX_RM_Admin
6Â months agoLNX_RM_Admin
6Â months agoSunshine2022
6Â months, 2Â weeks agokmsinthesky
6Â months, 2Â weeks agomesacgon
10Â months ago