Exam PMP topic 1 question 979 discussion

Actual exam question from PMI's PMP
Question #: 979
Topic #: 1
[All PMP Questions]

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

  • A. Meet with the project team to develop a proper resolution to the issue.
  • B. Request approval from the project sponsor to add more resources
  • C. Prepare documentation to explain the issue and communicate accordingly.
  • D. Update the project artifacts to reflect the new deadlines reported.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: A
A. Meet with the project team to develop a proper resolution to the issue
upvoted 1 times
...
517f9da
7 months, 2 weeks ago
Selected Answer: A
A. Meet with the project team to develop a proper resolution to the issue. Explanation: The first step is to collaborate with the project team to understand the issue and develop a resolution. This approach helps identify the root cause and promotes teamwork in finding a solution.
upvoted 1 times
...
Abdelmonm
11 months ago
Selected Answer: A
The project manager should do option A: "Meet with the project team to develop a proper resolution to the issue." By engaging with the project team, the project manager can collaborate on finding a solution to the challenges faced in completing the stories. This may involve assessing the reasons behind the delays, identifying possible adjustments or alternative approaches, and collectively deciding on the best course of action to ensure successful completion of the iteration.
upvoted 1 times
...
UppersquareCapital
11 months, 2 weeks ago
Selected Answer: A
Meeting with the project team is the first step to understand the nature of the issue and collaboratively identify potential solutions. This allows for open communication and shared problem-solving. Addressing the issue collaboratively with the project team helps in identifying the best course of action, whether it involves adjusting resources, reprioritizing work, or finding other solutions to ensure successful completion of the iteration.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago