Exam PMP topic 1 question 1052 discussion

Actual exam question from PMI's PMP
Question #: 1052
Topic #: 1
[All PMP Questions]

One of the team members is always late to the daily standup meeting. What should the project manager do?

  • A. Schedule the meeting at the end of the day to accommodate everyone.
  • B. Reinforce the ground rules for standup meetings with the entire team.
  • C. Speak with the team member directly to reinforce the ground rules.
  • D. Ignore the situation since the team member is accomplishing their deliverables.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
3 weeks, 2 days ago
Selected Answer: B
Realistically, I think it's C. However, in PMI, you can also think of it as B. I think this problem is very difficult and troublesome from the examinee's perspective. It is very difficult for me to judge what the answer is.
upvoted 1 times
...
sidje
4 months ago
Selected Answer: C
Communication directe et respectueuse : Parler directement avec le membre de l’équipe permet d’aborder le problème de manière respectueuse et constructive. Cela montre que le chef de projet est attentif et qu’il souhaite comprendre les raisons de ces retards tout en rappelant l’importance des règles de base. Solution ciblée : Une discussion en tête-à-tête permet de trouver une solution adaptée à la situation spécifique du membre de l’équipe. Peut-être y a-t-il des raisons valables pour ces retards qui peuvent être résolues par des ajustements mineurs. Maintien de la discipline et de l’efficacité : Renforcer les règles de base en privé aide à maintenir la discipline sans stigmatiser ou embarrasser l’employé devant ses collègues. Cela contribue à une meilleure ambiance de travail et encourage le respect des règles par tous.
upvoted 1 times
...
buvana
6 months, 1 week ago
The answer should be B and not C. Ww should reinforce to entire team.
upvoted 1 times
...
Davard
8 months ago
C makes the most sense, but I wouldn't be surprised if PMI prefers B.
upvoted 1 times
...
Abdelmonm
8 months, 1 week ago
Selected Answer: C
- Directly addresses the issue: Ignoring the situation can be considered disrespectful to other team members and undermines the importance of the standup meeting. - Provides an opportunity for understanding: A private conversation allows the project manager to uncover the reason behind the lateness and offer support if needed. - Reinforces accountability: Reminding the team member of the ground rules for standup meetings emphasizes its importance and their individual responsibility. - Maintains team dynamics: Ignoring the issue could cause resentment and disrupt team dynamics.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...