exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 323 discussion

Actual exam question from PMI's PgMP
Question #: 323
Topic #: 1
[All PgMP Questions]

After new private equity owners acquire an enterprise, they want to improve its value by reducing costs. A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed. A strategic component project presents significant risk to organizational objectives due to its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility. Implementation of this component project may now begin, but is already one month behind schedule. The program manager now perceives significantly more risk to the larger program due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?

  • A. Share the concerns with the program sponsor to confirm understanding of the new development. Next, update the program budget, implementation plan, and risk management plan for governance board approval.
  • B. Update the component project's risk register, issue log, implementation plan, and risk management plan. Next, meet with the program sponsor to revise the program budget, implementation plan, and risk management plan for governance board approval.
  • C. Revise the program budget, and implement the component project by managing it closely to recover the month-long delay. Next, update the component's project and risk management plans for governance board approval.
  • D. Update the program budget, and task the component project manager with implementing the plan. Next, submit a change order for approval to apply more resources to reduce the larger program's risk profile.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hanyulin
7 months, 2 weeks ago
Selected Answer: B
B is the best answer.
upvoted 1 times
...
happykaur
9 months, 2 weeks ago
Selected Answer: B
In this scenario, where a component project of a larger program is already behind schedule, increasing the risk to the overall program, the program manager should: B. Update the component project's risk register, issue log, implementation plan, and risk management plan. Next, meet with the program sponsor to revise the program budget, implementation plan, and risk management plan for governance board approval. This approach is comprehensive and proactive. It involves updating all relevant documentation and plans to reflect the current state of the project, including the increased risks due to the delay. By then meeting with the program sponsor and seeking governance board approval for the revised plans and budget, the program manager ensures that all changes are communicated effectively to key stakeholders and that the program aligns with the new reality. This process helps in managing the increased risk and seeks to keep the program on track despite the initial delays.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago