A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style.
Which landscape describes the project environment?
A. High accountability, little authority
Explanation: In a constantly changing business environment, a collaborative leadership style is often used to effectively manage the situation. This style works well in environments where the project manager has high accountability for project outcomes but limited authority over resources and decision-making processes.
In a constantly changing business environment, where the project manager decides to use a collaborative leadership style, the landscape is described as "High accountability, little authority." This means that the project manager is emphasizing collaboration and teamwork while facing challenges related to having limited decision-making authority. The team members may be held accountable for their work, but the project manager relies on collaboration and influence rather than strict authority to navigate the dynamic environment.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
5 days, 22 hours agoKim222
2 months, 2 weeks ago517f9da
6 months, 1 week agoUppersquareCapital
10 months, 2 weeks ago