Exam PMP topic 1 question 1018 discussion

Actual exam question from PMI's PMP
Question #: 1018
Topic #: 1
[All PMP Questions]

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

  • A. Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.
  • B. Continue working with the predictive approach to deliver the value at the end of the project.
  • C. Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.
  • D. Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month, 1 week ago
Selected Answer: D
D. Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client. This approach aligns with agile principles, focusing on delivering value incrementally and involving the client throughout the process. By breaking the work into smaller iterations, the project manager can ensure that the client receives early and continuous value, allowing for feedback and adjustments along the way. This transition to an agile mindset will benefit both the team and the client.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: D
D. Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: D
D. Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client Reviewing the backlog and creating small iterations allows the project to adopt agile practices effectively, delivering incremental value to the client throughout the project rather than waiting until the end, aligning with agile principles.
upvoted 1 times
...
Abdelmonm
10 months ago
Selected Answer: D
D. Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client. This option aligns with agile principles by advocating for an iterative and incremental approach. It allows for the delivery of incremental value to the client throughout the project, fostering adaptability and responsiveness to changes in requirements or client needs.
upvoted 1 times
...
chlaithem
10 months, 2 weeks ago
Selected Answer: D
Review backlog and create iterations (option D): This aligns perfectly with the agile mindset. Reviewing the backlog with the team allows identifying existing work items and restructuring them into smaller, deliverable iterations. This enables: Faster value delivery: Clients receive regular updates and actionable results, providing feedback and potentially shaping the project's direction. Reduced risk: Early feedback identifies potential issues sooner, allowing for course correction and adaptation. Increased team motivation: Delivering and showcasing progress keeps the team engaged and motivated.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.