Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.
What should the project manager do?
Trytrio
Highly Voted 9 months, 3 weeks agoAbdelmonm
Highly Voted 10 months agoMonBouj
Most Recent 1 month, 1 week agovictory108
1 month, 1 week ago9RedFox_JB
2 months, 4 weeks agosidje
6 months ago517f9da
6 months, 2 weeks ago517f9da
6 months, 2 weeks agokevzzz
8 months, 4 weeks agoKennyMuffins
9 months, 3 weeks agochlaithem
10 months, 2 weeks ago