As part of project execution, a contractor proposed and conducted site acceptance tests and pre-implementation technical training. However, during the implementation phase, the project manager notes a clear gap in the project team's competence in following the implementation of the technical requirements.

What should the project manager have done to avoid this situation?

  • A. Ensured the training conducted by the contractor used standard methods
  • B. Reviewed the proposed training with the contractor
  • C. Performed a proper training needs assessment
  • D. Prepared proper training outcome measurements
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 week, 3 days ago
Selected Answer: C
C. Performed a proper training needs assessment
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: C
C. Performed a proper training needs assessment Explanation: Conducting a proper training needs assessment would have identified the specific skills and knowledge gaps within the project team, ensuring that the training provided by the contractor was adequately tailored to address those gaps and fully prepare the team for the implementation phase.
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: C
To avoid a gap in the project team's competence during the implementation phase, the project manager should have performed a proper training needs assessment. This involves identifying the knowledge and skills required for the team to successfully carry out the implementation of technical requirements. By understanding the training needs upfront, the project manager can ensure that the training provided by the contractor is aligned with the specific requirements of the project and addresses any gaps in the team's competence.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...