A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project manager has a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.
Which tool is the project manager using?
mengyaoyao
2Â weeks, 5Â days agoAmirov
3Â weeks, 1Â day agovictory108
3Â weeks, 2Â days agoMonBouj
1Â month ago23169fd
1Â month, 1Â week agoAzharmak
4Â months, 2Â weeks agosidje
6Â months agosidje
6Â months agoLNX_RM_Admin
6Â months agohoomz
9Â months agoUppersquareCapital
9Â months, 3Â weeks agoTrytrio
9Â months, 3Â weeks agoLovejeetK
10Â months agokevzzz
10Â months, 2Â weeks agoAbdelmonm
10Â months, 2Â weeks ago