Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1080 discussion

Actual exam question from PMI's PMP
Question #: 1080
Topic #: 1
[All PMP Questions]

A bank has initiated a project to replace an existing core system with a new one. The system will be launched in several stages after the completion of each project deliverable that must be approved by the key stakeholders.

What should the project manager do first?

  • A. Engage experienced key stakeholders in the implementation of the project.
  • B. Review the test and inspection plan with the key stakeholders.
  • C. Agree on quality standards with the key stakeholders.
  • D. Develop a requirements traceability matrix.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: C
C. Agree on quality standards with the key stakeholders
upvoted 1 times
...
CECILIAmin
8 months, 3 weeks ago
We should first determine the demand, and then determine the quality standard, and the quality standard is also determined according to the demand. How to determine the quality criteria if the requirements are not certain
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: C
C sounds more immediate (general standard). The RTM can be developed in the next step and is more detailed.
upvoted 1 times
...
UppersquareCapital
10 months, 1 week ago
Selected Answer: D
In a project to replace an existing core system, developing a requirements traceability matrix (RTM) is a fundamental step. The RTM helps establish a clear link between the project requirements and the corresponding deliverables. This matrix is essential for tracking whether each requirement is addressed and fulfilled through the project stages. Once the requirements traceability matrix is in place, it becomes easier to engage key stakeholders, review the test and inspection plan, and agree on quality standards. The RTM provides a structured approach to ensure that the project is aligned with the agreed-upon requirements, making subsequent discussions and plans more effective and relevant to the project's objectives.
upvoted 2 times
...
jtr393
10 months, 2 weeks ago
Selected Answer: C
Understanding of quality standards with key stakeholders is "FIRST" thing the manager needs to do, then work on the Requirements Traceability Matrix
upvoted 2 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: C
Before initiating the project and proceeding with the implementation, it's essential to establish a common understanding of quality standards with key stakeholders. This ensures alignment on the expected level of quality for each deliverable and helps in preventing misunderstandings or disputes later in the project. Developing a Requirements Traceability Matrix (RTM) is an important step in project management, particularly in ensuring that all requirements are addressed throughout the project lifecycle. However, in the context of the scenario described, the question is focused on the initial steps to be taken when initiating a project to replace an existing core system. In summary, agreeing on quality standards (Option C) is a more immediate and foundational step when initiating a project, setting the stage for subsequent activities, including the development of a Requirements Traceability Matrix.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...