Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1059 discussion

Actual exam question from PMI's PMP
Question #: 1059
Topic #: 1
[All PMP Questions]

A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides with the company's financial budget planning period.

Which two actions should the project manager take next to address this concern? (Choose two.)

  • A. Advise the sponsor that it is not feasible to determine if the end date will be met as the project is in the initiation phase
  • B. Facilitate a risk workshop with all stakeholders in attendance to identify and assess all risks to the project
  • C. Log the concern as a risk in the project risk register and assess the impact and severity of the risk
  • D. Change the project implementation date so that the concern is alleviated and no longer applicable
  • E. Communicate to the project sponsor that the implementation date is low risk and will not impact the project
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: BC
B. Facilitate a risk workshop with all stakeholders in attendance to identify and assess all risks to the project C. Log the concern as a risk in the project risk register and assess the impact and severity of the risk
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: BC
Evaluate and analyze.
upvoted 1 times
...
grey7744
5 months, 3 weeks ago
B AND D
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: BC
B and C
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: BC
B. Facilitate a risk workshop with all stakeholders in attendance to identify and assess all risks to the project. C. Log the concern as a risk in the project risk register and assess the impact and severity of the risk. In this situation, the project manager should proactively address the concern by engaging stakeholders in a risk workshop to identify and assess potential risks to the project. This includes assessing the risk related to the project implementation date coinciding with the company's financial budget planning period. Logging this concern in the project risk register and assessing its impact and severity will provide a structured way to manage and mitigate the risk throughout the project lifecycle. It allows the project manager to develop a risk response plan and keep the sponsor informed about the actions taken to address the concern.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...