Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1054 discussion

Actual exam question from PMI's PMP
Question #: 1054
Topic #: 1
[All PMP Questions]

A client has requested that a product be implemented in 4 months and is ready to increase their budget to do this quickly. The project manager cannot comply with the request with the current resources or even additional resources. The project manager estimates that 8 to 12 months are needed for the product to go live.

What should the project manager do to address this situation?

  • A. Motivate the team to work more efficiently and approve overtime in order to meet the client's goal in 4 months
  • B. Seek additional resources from the subcontractors and other sources to parallelize the necessary work
  • C. Discuss with the client alternative approaches to deliver the minimal viable product (MVP) in 4 months and the rest later
  • D. Call a meeting with the client so they will understand that 4 months is not enough time to deliver the product
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: C
C. Discuss with the client alternative approaches to deliver the minimal viable product (MVP) in 4 months and the rest later
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: C
In this situation, it's important for the project manager to engage in open and transparent communication with the client. Since the client is willing to increase the budget to expedite the project, discussing alternative approaches to deliver a minimal viable product (MVP) within the client's desired timeframe is a pragmatic solution. The project manager can explore phased delivery, prioritizing essential features for the initial release and deferring less critical functionalities to subsequent phases. This allows the project to meet the client's urgent needs while ensuring a more realistic timeline for the entire project. Open communication about project constraints and possibilities is crucial for managing client expectations effectively.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...