Exam PMP topic 1 question 1047 discussion

Actual exam question from PMI's PMP
Question #: 1047
Topic #: 1
[All PMP Questions]

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

  • A. Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software
  • B. Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software
  • C. Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained
  • D. Request a meeting with the sponsor to change the scope to allow the development team to conduct testing
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: C
C. Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained C is the best choice because it promotes collaboration with the project team to find a viable solution for the testing support needed, ensuring that all perspectives are considered and maintaining the project’s momentum
upvoted 1 times
...
victory108
1 month ago
Selected Answer: C
C. Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: C
In a matrix organization, where project managers often work with resources borrowed from functional managers, collaboration is key. If the functional manager is unable to provide resources for testing, the project manager should work with the project team to explore alternative solutions and determine how to ensure that the necessary testing support is obtained. This may involve negotiating with other functional managers, adjusting the project schedule, or finding external resources. The focus should be on finding a collaborative and practical solution within the project team.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.