A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee:

• Actual progress = 2 units
• Planned progress = 3 units
• Actual cost (AC) = 2 units
• Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

  • A. The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted
  • B. The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken
  • C. The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities
  • D. The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: C
C. The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: C
A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee: • Actual progress = 2 units • Planned progress = 3 units • Actual cost (AC) = 2 units • Budgeted cost = 3 units What statement should the project manager make to the project steering committee? A. The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted B. The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken C. The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities D. The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings
upvoted 2 times
Abdelmonm
9 months, 4 weeks ago
C. The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities. This statement accurately reflects the situation where the project is behind schedule (Actual progress < Planned progress) but is incurring lower costs (AC < Budgeted cost). It also communicates the proactive approach of making efforts to expedite delayed activities to mitigate the schedule slippage.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...