Exam PMP topic 1 question 1039 discussion

Actual exam question from PMI's PMP
Question #: 1039
Topic #: 1
[All PMP Questions]

The sponsor of a newly formed agile project is struggling to understand the scope and to determine when critical product features will be ready to use. What should the project manager do?

  • A. Move the team’s kanban board to a more visible place to improve the communication with key stakeholders.
  • B. Create a detailed project management plan with all planned releases and the tasks needed to deliver them.
  • C. Establish the project vision, break down the mam features backlog, prioritize, and create an overall release plan.
  • D. Invite the stakeholder to the project’s daily meetings, providing better visibility on what the team is working on.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
KellyT68
1 month ago
what is a mam feature?
upvoted 1 times
...
MonBouj
1 month ago
Selected Answer: C
C. Establish the project vision, break down the mam features backlog, prioritize, and create an overall release plan By establishing the vision, breaking down the backlog, and creating a release plan, the project manager can provide the sponsor with a clear understanding of the product scope and the timeline for critical feature delivery.
upvoted 1 times
...
victory108
1 month ago
Selected Answer: C
C. Establish the project vision, break down the mam features backlog, prioritize, and create an overall release plan
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: C
Creating a project vision, breaking down the features backlog, prioritizing, and creating an overall release plan are key steps in agile project management. This helps in providing clarity on the scope and timeline for critical product features. It ensures that the team and stakeholders have a shared understanding of the project goals, priorities, and timelines. This approach aligns with the principles of agile, emphasizing collaboration, adaptability, and delivering value iteratively.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.