Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1036 discussion

Actual exam question from PMI's PMP
Question #: 1036
Topic #: 1
[All PMP Questions]

A project is in the middle of the fifth iteration. Due to a sudden slump in the economy, the company recorded a drastic reduction in revenue. The strategic direction was to Implement cost-reduction measures immediately.

What should the project manager do next?

  • A. Continue the current sprint without interruption and address priorities in the upcoming product backlog grooming sessions.
  • B. Meet with the sponsor for guidance on the best path forward before executing sprints.
  • C. Allow the project team to decide on the best path forward for the current sprint.
  • D. Schedule a meeting with the product owner, discuss priorities and decide if anything from the backlog can be eliminated, based on current constraints.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: D
D. Schedule a meeting with the product owner, discuss priorities and decide if anything from the backlog can be eliminated, based on current constraints. Conclusion By engaging with the product owner to reassess the backlog, the project manager can make informed decisions that directly reflect the company's new focus on cost reduction while also ensuring that the project remains on track to deliver value.
upvoted 1 times
...
victory108
1 month ago
Selected Answer: D
D. Schedule a meeting with the product owner, discuss priorities and decide if anything from the backlog can be eliminated, based on current constraints
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: D
For sure its D ... you must align with the PO to find a common ground
upvoted 2 times
...
Delab202
10 months, 1 week ago
Selected Answer: D
In this scenario, the most appropriate action for the project manager would be: D. Schedule a meeting with the product owner, discuss priorities and decide if anything from the backlog can be eliminated, based on current constraints. While seeking guidance from the sponsor is valuable, it's more efficient first to assess the situation with the product owner who has a closer understanding of the project's day-to-day priorities and constraints.
upvoted 1 times
...
UppersquareCapital
10 months, 1 week ago
Selected Answer: D
This option involves proactive communication with the product owner to reassess priorities and make informed decisions regarding the backlog. Considering the economic constraints, the project manager and product owner can collaboratively identify features or tasks that can be deprioritized or eliminated to align with the cost-reduction measures. This approach allows for adaptability and responsiveness to the changing economic conditions without completely interrupting the ongoing sprint.
upvoted 1 times
...
chlaithem
10 months, 2 weeks ago
Selected Answer: B
Seek strategic direction: The sudden economic change likely requires adjustments to the project's strategic direction. Meeting with the sponsor ensures understanding of the revised priorities and how the project should adapt. Evaluate project viability: Discuss the project's value and contribution to the company's current needs in light of the cost-reduction measures. This could lead to decisions like: Continuing the project with revised scope or budget. Pausing or postponing the project. Redesigning the project to align with changed priorities. Clear communication and collaboration: Involving the sponsor early promotes transparency and ensures everyone is aligned on the revised path forward.
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: D
This option involves proactive communication with the product owner to assess priorities and make informed decisions about adjusting the backlog in response to the new economic constraints. It allows the project manager and product owner to collaborate on adapting to the changing circumstances while maintaining a focus on delivering value within the current constraints.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...